The schedule for the temporary installations of Paris 2024 in the area of the Grand Palais, Pont Alexandre III, and Les Invalides runs from April to October 2024.


  • Mid-April: Start of assembly on the southeast lawns of Les Invalides.

  • From mid-April to mid-June: Progressive expansion of the construction site across all the lawns of Les Invalides and on Avenue du Maréchal Gallieni; closure of Cours la Reine between Pont Alexandre III and Les Invalides from April 26 onwards and occupation of Pont Alexandre III and the nearby lower quays from May 17 onwards.

  • From September to late October: Gradual release of the Champ-de-Mars.